Production of project documentation for the construction of accessible roads and deviations of existing roads for the construction of the second railway line Divača Koper

Production of project documentation for the construction of accessible roads and deviations of existing roads for the construction of the second railway line Divača Koper

As part of the project, we produced the project documentation for the arrangement of accessible roads to tunnels and viaducts on the 2nd railway line Divača-Koper, as well as the arrangement of the deviations of existing roads on the route of the railway line.

In addition to over 20 km of roads with different transverse profiles and reinforcements, the project includes the construction of culverts and bridges, supporting and retaining structures, water management, and the implementation of stormwater drainage and water supply system.

 

Investor:

Ministry of Infrastructure, Directorate of the Republic of Slovenia for Infrastructure, Tržaška cesta 19, 1000 Ljubljana

Production phase:

PGD and PZI

Year of production:

2009 – 2011 (PGD), 2017 (PZI)

Legend:

*PGD = project for acquisition of building permit *PZI = project for execution

This website uses cookies to give you the best, most relevant experience. Using this website means you are OK with this. You can change which cookies are set at any time – and find out more about them – by following this link. With clicking CONTINUE cookie is created, where it's memorized you want to hide this pop-up text. Cookie will not save any personal information.